Connection Form


MainPower requires the Connection Application Form provided below to be filled in by an electrician, builder or customer as appropriate in all instances where a connection to the distribution system is required in order to deliver electricity to a consumer.

The form can be filled in online and submitted with electronically attached plans however if you prefer to print the form out, fill it in and fax or deliver it with attached plans then click here for a printable version.

Electricians-please review this information relating to important requirements when applying for connections to our distribution system which should provide some assistance with the connection process. MainPower looks forward to assessing your application and connecting you to our distribution system.

Note: Where fields are not applicable, please put N/A. Form will not submit with blank fields.

Customer/Builder Name Enquiries Ph 03-311-8300

First Name/Builder : Surname :
Phone : Mobile :

Connection Location

Rapid/St Number: Street Name:
Area :

Survey Plan

DP :
Main Power Job Number(if known) : Closest Transformer Number :

Electrician Details

First Name : Surname :
Mobile :

A. Connection Type

Connection Type





Proposed Connection Date

Date(dd/mm/yyyy) :

ICP 0000


B. Builders Temp Supply

C. Servicemain Details

Type: Metered
Location at: Boundary Meter Box
Servicemain installed by : MainPower
Electrician
Other (specify)
Connection Charge :

Customer / Builder Electrician

Service Main:

Size : mm2
Length : m
Type : Cu Al
Monthly Supply Charge :
Customer / Builder Electrician

D. Chosen Retailer

Customer's Selection :

Connection of a temporary supply does not constitute approval for a final connection. A separate application must be submitted for a final supply connection.

Electrician to Complete

Compliance Certificate Number : Proposed Generation : kW
Location of Compliance Certificate on Site : Installation Description
House
Shed
Pump
Business
Water Heater Type
Solar
Controlled
Uncontrolled
Gas
None
Maximum Demand : Amps/phase
Phases for connection : 1 phase
3 phase
Irrigation Total Capacity: kW
VFD Capacity :

F. Permanently Unmetered Supply

Largest Motor Details : 1 phase 3 phase
Capacity : kW
Starting Method :
Description : Connected Watts : W
Daily Operating : hrs

Links referenced
here
http://www.mainpowertrust.org.nz/index.cfm/3,369,516/appforconnection1210.pdf
this information
http://www.mainpowertrust.org.nz/index.cfm/3,369,516/webeletricianreminders.pdf

Location http://www.mainpowertrust.org.nz/index.cfm/1,369,0,43,html


MainPower New Zealand Limited and UtilityOnline

5 High Street
PO Box 346
Rangiora 7440
New Zealand

Ph 03 311 8300
Fax 03 311 8301

Email info@mainpower.co.nz

Faults within the MainPower area: Ph 0508 60 70 80